Burlington, VT
Joseph Architects, LLC
Budget: $1.2 Million
Completed: April 2008
Stewart Construction was hired by Fletcher Allen Healthcare of Burlington in August of 2007 to upgrade their Baird 6 patient floor.
With operating floors above and below the renovation Stewart Construction was able to complete the entire project over a four phase 22 week construction schedule. The renovations included demolition and replacement of the bathrooms in each of the patient suites, replacement of the nurse call system, installation of new patient monitoring equipment, reconfiguration of the nurse’s station, and upgrades to the finishes in all of the public areas within Baird 6. Stewart Construction also added a new state of the art bariatric suite.